December 2022

< back

December 2022



Tender


In the last quarter, much time and effort has gone into getting the tender steam heat and vacuum pipework to fit correctly, with the pipes stripped down to component parts where necessary and new sections fitted.


Threaded joint sections have been welded in to both pipe runs and several brackets adjusted and extended to the correct length. This is now largely complete with a couple of new brackets required under the front dragbox to replace corroded originals and the pipe work requiring removing, painting and final fitting. 

A start has been made on replacing the parts stolen in July, with over twenty new brake pull rod and spring hanger pins machined.


We are currently trying to get quotes for replacing the stolen inside valve gear, but this is proving difficult due to the lack of companies able or willing to forge one-off steel components.